mirror of
https://repo.getmonero.org/monero-project/ccs-proposals.git
synced 2024-12-18 12:24:31 -05:00
61 lines
1.9 KiB
Markdown
61 lines
1.9 KiB
Markdown
---
|
|
layout: cp
|
|
title: selsta part-time monero development (3 months)
|
|
author: selsta
|
|
date: 8 Jul 2021
|
|
amount: 90
|
|
milestones:
|
|
- name: July
|
|
funds: 33% (30 XMR)
|
|
done: 31 July 2021
|
|
status: finished
|
|
- name: August
|
|
funds: 33% (30 XMR)
|
|
done: 31 August 2021
|
|
status: finished
|
|
- name: September
|
|
funds: 33% (30 XMR)
|
|
done: 30 September 2021
|
|
status: finished
|
|
payouts:
|
|
- date: 17 August 2021
|
|
amount: 30
|
|
- date: 15 September 2021
|
|
amount: 30
|
|
- date: 15 October 2021
|
|
amount: 30
|
|
---
|
|
|
|
## What
|
|
|
|
- Smaller dev work on CLI and GUI
|
|
- Some things I worked on last proposal
|
|
- Remove outdated monero unbound submodule, update it for deterministic builds (CLI)
|
|
- Set up a depends package source backup (CLI)
|
|
- Fix clang warnings (CLI)
|
|
- Add support for outputs import / export (GUI)
|
|
- Set minimum Qt version to 5.12, cleanup codebase and cmake file (GUI)
|
|
- Fix small design inconsistencies (GUI)
|
|
- Re-add password strength meter (GUI)
|
|
- Put effort where necessary
|
|
- Testing and reviewing pull requests (CLI, GUI, site)
|
|
- Monero release engineering for CLI and GUI
|
|
- Organizing what goes into a release
|
|
- Compiling CLI and GUI, packaging for distribution
|
|
- Writing release notes
|
|
- Misc work (user support, issue tracker maintanace)
|
|
|
|
## Who
|
|
|
|
selsta, I have been contributing to monero since around 2018 with over 420 merged commits. Here is a list of my previous work:
|
|
|
|
- CLI contributions: https://github.com/monero-project/monero/pulls?q=is%3Apr+author%3Aselsta
|
|
- GUI contributions: https://github.com/monero-project/monero-gui/pulls?q=is%3Apr+author%3Aselsta
|
|
- Previous CCS: https://ccs.getmonero.org/proposals/selsta-1.html
|
|
|
|
If funded I will provide monthly updates in the CCS comment section.
|
|
|
|
## Proposal
|
|
|
|
Work for 30 hours per week over the next 3 months (from Mid July to Mid September) at a rate of 45€ / hour. At 180€ / XMR (14 day EMA) this makes 90 XMR.
|