@ -12,7 +12,8 @@ title: Version scheme
|
||||
|
||||
The Qubes OS Project uses the [semantic versioning](https://semver.org/)
|
||||
standard. Version numbers are written as `<major>.<minor>.<patch>`. When
|
||||
`<patch>` is zero, it is often omitted as a matter of convention, e.g., `4.1`.
|
||||
`<patch>` is zero, it is often omitted as a matter of convention, e.g., `4.1` is
|
||||
short for `4.1.0`.
|
||||
|
||||
In general, patch releases are for backward-compatible bug fixes, minor
|
||||
releases are for backward-compatible enhancements and new features, and major
|
||||
@ -28,11 +29,11 @@ contrast, **release** refers to any version that is intended for consumption by
|
||||
the general userbase. For example, `4.0.4` was both a **version** and a
|
||||
**release**, since it was stable and intended for general public use, while
|
||||
`4.1-beta1` was a **version** but *not* a **release**, since it was not stable
|
||||
and was intended only for [testing](/doc/testing/). All **releases** are
|
||||
**versions**, but not all **versions** are **releases**.
|
||||
and was intended only for [testing](/doc/testing/). All releases are
|
||||
versions, but not all versions are releases.
|
||||
|
||||
The letter **R**, as in `R4.1` stands for **release**. The abbreviation **RC**,
|
||||
as in `3.2-rc2` stands for **release candidate**.
|
||||
The letter **R**, as in `R4.1`, stands for **release**. The abbreviation **RC**,
|
||||
as in `3.2-rc2`, stands for **release candidate**.
|
||||
|
||||
## Qubes distributions and products
|
||||
|
||||
@ -72,35 +73,36 @@ Issues in our [issue tracker](/doc/issue-tracking/) are sorted by release
|
||||
|
||||
## Release schedule
|
||||
|
||||
There is no specific schedule for releases other that more general
|
||||
roadmap. When time comes, Supreme Committee declares feature freeze and tags
|
||||
`-rc1` and releases ISO image. From this time on, no new features are accepted.
|
||||
Also a strict time schedule kicks in.
|
||||
There is no specific schedule for releases other that more general roadmap.
|
||||
When time comes, Supreme Committee declares feature freeze and tags `-rc1` and
|
||||
releases ISO image. From this time on, no new features are accepted. Also a
|
||||
strict time schedule kicks in.
|
||||
|
||||
Each release candidate period is as follows. For the first two weeks we accept
|
||||
and assign bug reports to be fixed before next release candidate. For the next
|
||||
two weeks we generally focus on fixing assigned bug reports, so issues discovered
|
||||
during this time may be postponed until later RC. Finally after that there is
|
||||
one week of current-testing freeze, during which time no new packages are
|
||||
released, in hope that they will be installed by wider user base and tested.
|
||||
two weeks we generally focus on fixing assigned bug reports, so issues
|
||||
discovered during this time may be postponed until later RC. Finally after that
|
||||
there is one week of current-testing freeze, during which time no new packages
|
||||
are released, in hope that they will be installed by wider user base and
|
||||
tested.
|
||||
|
||||
The next RC is released five weeks after the former. All packets are published
|
||||
in `current` repository and the cycle starts over. There should be no less than
|
||||
1 and no more than 3 release candidates before final release.
|
||||
|
||||
| stage | time |
|
||||
| Stage | Duration |
|
||||
| ------------------------ | --------- |
|
||||
| initial testing | two weeks |
|
||||
| bug fixing | two weeks |
|
||||
| `current-testing` freeze | one week |
|
||||
|
||||
Starting with second cycle (that is, after `-rc1`) two weeks into the cycle
|
||||
(after primary bug-reporting period) the Supreme Committee decides whether there
|
||||
should be another RC. If, based on remaining issues, the Committee decides to
|
||||
release final, then the Committee agrees upon the release date, which should be
|
||||
no later than a week after.
|
||||
(after primary bug-reporting period) the Supreme Committee decides whether
|
||||
there should be another RC. If, based on remaining issues, the Committee
|
||||
decides to release final, then the Committee agrees upon the release date,
|
||||
which should be no later than a week after.
|
||||
|
||||

|
||||